Road Information for Week of June 27-July 2

Construction on Interstate 30 Requires Lane Closures in Little Rock and North Little Rock
Posted on 06/28/2021

Construction on Interstate 30 Requires Lane Closures in Little Rock and North Little Rock

Mon., Wed., Thurs., June 28, 30, July 1 |8 p.m. – 5 a.m.

I-30 westbound in Little Rock | Overnight single and double-lane closures between 4th St. and I-630. Double-lane closures will be limited to 11 p.m. to 4 a.m.


Mon., June 28 – Thurs., July 1 | 10 p.m. – 5 a.m.

Broadway St. | Overnight full street closure between I-30 frontage roads. Single-lane closures will begin at 8 p.m. Detour will be signed to use Bishop Lindsey Ave. and Riverfront Dr. See detour map NR 21-202-B below for details.

 

Mon., June 28 – Tues., June 29 | 10 p.m. – 5 a.m.

I-630 eastbound ramp to I-30 eastbound (Exit 139 A) | Full ramp closure during overnight hours. Detour will be signed to use Exit 139B to Roosevelt Rd. See detour map NR 21-202-C below for details.


Mon., June 28 – Thurs., July 1 | 8 p.m. – 5 a.m.

I-30 eastbound in Little Rock | Overnight single and double-lane closures between I-630 and the Cantrell Interchange. Double-lane closures will be limited to 10 p.m. to 5 a.m.


Tues., June 29 – Thurs., July 1 | 8 p.m. – 5 a.m.

I-30 eastbound in North Little Rock | Overnight single and double-lane closures between the Arkansas River and Bishop Lindsey Ave. Double-lane closures will be limited to 10 p.m. to 5 a.m.

Traffic will be controlled by construction barrels and signage. Drivers should exercise caution when approaching and traveling through all highway work zones.

Map A
Map B
Map C